1. Technical parameter
Dedusting mode: EAF is 4th hole + canopy, LF is 4th hole.
1.1 Long bag type dust collector
| SN | Item | Unit | Data | Remark |
| 1 | Type | LLP10000 | ||
| 2 | Quantity | set | 1 | |
| 3 | Filter bag | °C | ≤120 | |
| 4 | Bag material | Water and oil repellent polyester needle felt | ||
| 5 | Filter area | 10000 | ||
| 6 | Fume speed at filter | m/min | ≤1.2 | |
| 7 | Fume amount | m3/h | 600000 | |
| 8 | Filter bag size | mm | φ130×6000 | |
| 9 | Filter bag quantity | pcs. | 4100 | |
| 10 | Pulse vavle quantity | pcs. | 240 | |
| 11 | System resistance | Pa | <1500 | |
| 12 | Dust emission concentration | mg/ Nm3 | <50 | |
| 13 | Dust cleaning control | PLC | Pulse type, off line | |
| 14 | Dust room | nos. | 16 | |
| 15 | Dust removal mode | Mechanical conveyor | ||
1.2 De-dusting fan & motor
| SN | Item | Unit | Data | Remark |
| 1 | Fan model | Y4-73No25F (T) | ||
| 2 | Quantiy | set | 1 | |
| 3 | Fan delivery | m3/h | 600000 | |
| 4 | Fan aire pressure | Pa | 4200 | |
| 5 | Motor power | 1250kW | 10kV | |
| 6 | Quantiy | set | 1 | |
| 7 | Motor speed | rpm | 960 | |
| 8 | Protection class | IP44 |
2. Supply list & breakdown price
| SN | Item | Unit | Qty | Remark |
| A | Mechanical part | |||
| 1 | Main fume pipeline | t | 150 | |
| 2 | Water cooled pipeline | m | 50 | For EAF |
| 3 | Water cooled pipeline | m | 30 | For LF |
| 4 | Pneumatic butterfly valve | set | 1 | |
| 5 | Air mixing valve | set | 1 | |
| 6 | EAF fan | set | 1 | |
| 7 | EAF motor | set | 1 | |
| 8 | Noise insulation & reduction part | set | 1 | |
| 9 | Fluid transmission couplier | set | 1 | |
| 10 | Bag type dust collector | t | 330 | |
| 11 | Air tank | set | 1 | 5m3 |
| 12 | Freeze dryer | set | 1 | 5m3 |
| 13 | Compressed air triplet set | set | 1 | |
| 14 | Pipeline fittings | set | 1 | |
| 15 | Air source treatment part | set | 1 | |
| 16 | Star dust unloader valve | set | 18 | DF300 |
| 17 | Screw dust conveyor | set | 2 | φ30/φ40 |
| B | Electrical part | |||
| 1 | H.V. incoming panel | pc. | 1 | |
| 2 | H.V. breaker panel | pc. | 1 | |
| 3 | Liquid resistance starter panel | pc. | 1 | |
| 4 | HMI panel | pc. | 1 | |
| 5 | PLC panel | set | 1 | Siemens S7-300 |
| 6 | GGD panel | pcs. | 4 | |
| 7 | Field junction box | pc. | 4 | |
| C | Others | |||
| 1 | Package, customs, doucments | 1 | ||
| 2 | Installation material | 1 | ||
| 3 | China transportation | 1 | ||
| Total Price (FOB china port) | ||||
Supplied by the Buyer:
1) Installation, hydraulic medium, lubrication medium and cleaning medium;
2) Roof canopy (meltshop roof steel structure), pipeline supports, chimney;
3) Civil works and design (Seller provides furnace foundation drawings and civil work requirements),
embedded furnace foundation parts;
4) Water supply and gas supply main inlet are laid to Seller’s equipment connection point, 10kV
incoming line to Seller’s H.V. panel, L.V. are connect to Seller’s L.V. distribution panel.
3. Delivery: 6 month after the Seller receiving down payment.
Sales:
Our Best Service For You
| 1. | Pre sale service |
| a. | make technical solution |
| b. | send quotation, technical data sheet and drawing |
| c. | prepare power transmission plan, testing plan and shipment plan |
| 2. | In sale service |
| a. | supervise the manufacturing schedule totally in accordance with the plan |
| b. | send photos to customer during every manufacturing process(hold point) |
| c. | inform the customer one week before testing. |
| 3. | After sale service |
| a. | installation and commissioning, training the workers |
| b. | quick response within 12 hours any time |
| c. | provide 12 months guarantee period normally. |
FAQ For You
| 1. Q: | What is your delivery time ? |
| A: | Depend on the type of transformer. |
| 2. Q: | What is your payment term? |
| A: | 30% advance by T/T , 70% before delivery by T/T or L/C or we can discuss about it. |
| 3. Q: | What kind of standard you follow? |
| A: | IEC, ANSI, GB, etc |
| 4. Q: | What kind of supporting documentation you can provide normally |
| A: | Quotation, outline drawing, manufacturing plan, quality control plan testing plan, financial report, type test report(KEMA, CESI),reference list, etc |
| 5. Q: | What is your normal warranty period? |
| A: | 12 months after transformer operation. |
| 6. Q: | Can u do installation and commission in user’s site? |
| A: | Yes, we can send our installation team to user’s country for service. |
| 7. Q: | Do you have any experience in this kind of transformer? |
| A: | Yes, we can provide reference list for check. |
Our advantages:
Quality Assurance
–From the very beginning, VILLE ensures quality in every step to achieve the best quality.
Experience Sharing
–With more than 30 years’ experience in power industry, VILLE brings you an optimized solution.
Global Service
–Wherever you are, VILLE global network will support and provide you with value.
Quick Response
–In response to your needs without delay, VILLE knows the value of your time.
Thanks for choosing VILLE as your reliable partner and
please trust both of us will create a brilliant future!
/* January 22, 2024 19:08:37 */!function(){function s(e,r){var a,o={};try{e&&e.split(“,”).forEach(function(e,t){e&&(a=e.match(/(.*?):(.*)$/))&&1
We are China 50t Eaf & 50t Lf De-Dusting System manufacture and supplier,You can get more details with Email,you will get cheap price or factory price.
Get Latest Price Request a quote
Popular 50t Eaf & 50t Lf De-Dusting System Products
Popular cnville Products
Lb7-220 Type Oil-Immersed Fully-Sealed Structure Current Transformer
Fire Extinguisher System for Transformer
Double-Breathing Hygroscopic Apparatus for Transformer, Silica Gel Breather